Is there a basis for the compaction factor of 228?
Bai Qingting asked: "Is this 41 yuan per cubic meter unit price is the inquiry?"
Lin Yiping replied: "Yes, it is coming."
Bai Qingting asked: "How is the unit price of 41 yuan?"
Lin Yiping replied: "In the inquiry process, you need to know more carefully. I am afraid that it is covered by suppliers, so they ask suppliers to provide chartering, negotiation."
Bai Qingting nodded: "If this is, at least it is better, knowing to learn more detailed information. Inquiry, have you inquired a few people?"
Lin Yiping replied: "Because this bid is more tense, only two prices are present, their prices are almost."
Bai Qingting arranged: "Song, after the opening of this meeting, we must strengthen the inquiry work, then inquire, the difference between the earth is more big."
Song Zhiyuan: "Okay, white, we are the price of the Division, the estimated accuracy will be somewhat, after opening the meeting, I will let the Zhao Manfu tablets will arrange people to find the landworks of the project. Learn about the price. "
Zhao Manfu replied: "Song's total, white, we have arranged the inquiry work of the earth, but the preparation meeting is more early, so I haven't got a single price. I will urge it to urge it. "
Bai Qingting replied unsatisfactory: "Zhao, what is early, only a few days, the inquiry work must be strengthened, this time has been dragged for a long time, which will cause cost analysis inaccurate, not conducive to Win a bid. "
Zhao Manfu replied: "Okay, white, I must strengthen the inquiry work."
Bai Qingting continued to ask: "The car is compressed into a substantially 1.4 cubic meter to compact it into 1 cubic meter. Is this data as a basis?"
Lin Yiping replied: "There is currently not much basis, mainly the experience data provided by the supplier team."
Bai Qingting replied: "Is it just right with experience data? Isn't it a quota? Are you checked the data above?"
Lin Yiping replied: "There is no grading."
Bai Qingting asked: "Is there a person in charge of the area where the project is located?"
Zhao Manfu replied: "The person in charge of the area of the area is Zhang Yunqing, come back, you stand up."
Zhang Yunqing listened to Zhao Manfu and stood up and replied: "Chairman, I am Zhang Yunqing, head of the area of the area."
Bai Qingting asked Zhang Yunqing: "Do you know that the location of the project is the true side of this earth, the physical relationship?"
Zhang Yunqing replied: "Know that there is a floor volume variable table in the quota.
Natural density volume 1 cubic meter is equivalent to a virtual volume of 1.3 cubic meters, equivalent to a solids volume of 0.87 cubic meters, equivalent to loose volume 1.08 cubic meters. "
Bai Qingting: "Then, the car is a true side, 20 yuan per side, changing the loose filler = 20 * 1.31.08 = 24 yuan, each of the 28 yuan per square, the cost is less than 4 Yuan per square. "
Zhao Manfu listened to Bai Qing Ting and replied: "Bai always, there may be a difference in theoretical value and actual value. Although it is loosened, it is still a very heavy car in the actual operation. Soil, equivalent to a partial rolling, a mutin car is also at least four, fifty tons, and these weights are in a few tires, and his actual rolling effect is not much lower than the upper pressure road. So If the calculated, it may be more optimistic in cost. "
Bai Qingting asked: "What do you say?"
Zhao Manfu replied: "I think that in the current situation, we can check the price of several suppliers. The requirement is to confirm his return equivalent in the style of square grid, and the price should consider the material to present. Inner transport, backfilling, rolling, etc., so that we are consistent with the theory of the above-in-law, you can avoid the problem of losses in this area.
Bai Qingting replied: "Well, this is a feasible method, is there?"
Zhao Manfu replied: "There is also the problem of this compaction coefficient. In fact, the impact on our pricing is relatively large. We can understand these prices, then follow the regular method, finally measured Look at the amount of square, then add all the costs to this actual backfill, and then get the actual cost of our earth. "
Bai Qingting said: "The experiment is also better, but everyone knows that this plantation has a time difference with our actual delivery, this time difference will cause a certain amount of settlement, this settlement amount How to solve the difference? "
Zhao Manfu replied: "This amount of settlement is poor, in fact, the compaction is related to the backfill, the compaction is good, but this is also a lot of work in our industry, I am in the original According to the statistics in the project, the percentage of the decrease in the construction volume brought about from 5% -15%. "
Bai Qingting is more satisfied with his head: "Well, everyone will be like Zhao Manfu, in the usual work, in the measurement cost and on-site work arrangement, it can really do it. This planting cost is still high. I have dot, after the meeting, I have worked hard and put the cost unit price more clearly.
Ok, Xiaolin you continue to report. "
Lin Yiping continued to report: "The government construction project is 25 million yuan, and the list of list is very much. If you look by, it is estimated that you can't finish the day."
Bai Qingting said: "Xiaolin, the number of lists in the garden is mostly understandable, but the number of bits that are not repeated in the garden should be not much, you put the main typical cost unit prices on the projection to everyone to see , Then you explain the composition of your cost. "
Lin Yiping replied: "Okay, white.
The main typical cost of planting project has a plain soil consolidated, even a sandstone pad, a cushion, a concrete, a wall body, a steel baffle, steel template, brick foundation, brick wall, cement mortar wall plaster , SBS roll material waterproof, steel structure production installation, wood structure production installation, stone laying, procurement prices of various main materials such as stone purchase price, SBS coil purchase price, etc. "
After Lin Yiping said, he looked up and looked at everyone. He watched no one asked questions. "" First, this simplest vegetarian is constructed, we are here, 1 yuan per square meter, consider One of the ordinary dried days can be consolidated one hundred square meters, and the unit price of ordinary workers is 90 yuan daily, the mechanical complement fee is 10 yuan a day.
Is there a different opinions? "
Lin Yiping saw that everyone did not speak, and then told one of them.